Report for June 2016

Report Date
June 2016

Achievements in Last Period

  • New bugs for Direct Admission Supervisors released to live
  • Bug fixes relating ot Student Hub issues in progress for release with SAC 50/51 on 25th July
  • Agreement from IS Apps that the fixes will address the outstanding issues and allow for project closure and handover

 

Resolved issues

  • Delay in closure to resolve bugs and change of PM (PICCL 10)

 

Open issues 

  • 3 new Unidesk issues raised since PICCL.  These are under consideration for including in release on 25th July if small fixes.

 

Next Steps

  • Release final bug fixes
  • Complete handover to support
  • Closure

 

 

25-Jul-2016DSOR Sign Off
29-Jul-2016Closure
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
AMBER
Overall
AMBER
Change Status
Activity
Approved budget
227.0 days
Activity this month
2.0 days
Activity this year
244.0 days
Activity to date
244.0 days
Estimate to complete current year
4.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Re-Design Student Hub
Code
SAC049
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Karen Osterburg
Project Sponsor
Barry Neilson
Current Stage
Close
Status
Closed
Start Date
27-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Programme Priority
3
Overall Priority
Normal
Category
Discretionary

Documentation