Report for June 2016
- Report Date
- June 2016
Achievements in Last Period
- New bugs for Direct Admission Supervisors released to live
- Bug fixes relating ot Student Hub issues in progress for release with SAC 50/51 on 25th July
- Agreement from IS Apps that the fixes will address the outstanding issues and allow for project closure and handover
Resolved issues
- Delay in closure to resolve bugs and change of PM (PICCL 10)
Open issues
- 3 new Unidesk issues raised since PICCL. These are under consideration for including in release on 25th July if small fixes.
Next Steps
- Release final bug fixes
- Complete handover to support
- Closure
| 25-Jul-2016 | DSOR Sign Off |
| 29-Jul-2016 | Closure |
- Approved budget
- 227.0 days
- Activity this month
- 2.0 days
- Activity this year
- 244.0 days
- Activity to date
- 244.0 days
- Estimate to complete current year
- 4.0 days
- Estimate to complete future years
- 0.0 days