Report fir August 2015

Report Date
August 2015

Achievements in Last Period

  • Project budget agreed allocation made from SSP Programme Budget 135 days
  • Kick-Off meeting held with Student Systems Management
  • Project Sponsor agreed 
  • Deliveries agreed as View Only Version then full update version
  • Work on framework started

Issues

  • No current issues

Next Steps 

  • Complete foundation stage including framework developed in SITS
  • Complete and submit project brief
  • Complete stories for all phases including feedback from user sessions
  • Contact user group confirm deliver strategy

 

Milestones

11-Sep-2015Project Brief Complete
25-Sep-2015Foundation Stage Complete - Framework Developed
30-Oct-2015View Only Student Hub Complete
09-Nov-2015Deliver View Only Hub (Limited set of users)
15-Jan-2016Update Student Hub Complete
21-Jan-2016Deploy to Live
19-Feb-2016DSOR Sign Off
04-Mar-2016Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Re-Design Student Hub
Code
SAC049
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Karen Osterburg
Project Sponsor
Barry Neilson
Current Stage
Close
Status
Closed
Start Date
27-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Programme Priority
3
Overall Priority
Normal
Category
Discretionary

Documentation