Report fir August 2015
- Report Date
- August 2015
Achievements in Last Period
- Project budget agreed allocation made from SSP Programme Budget 135 days
- Kick-Off meeting held with Student Systems Management
- Project Sponsor agreed
- Deliveries agreed as View Only Version then full update version
- Work on framework started
Issues
- No current issues
Next Steps
- Complete foundation stage including framework developed in SITS
- Complete and submit project brief
- Complete stories for all phases including feedback from user sessions
- Contact user group confirm deliver strategy
Milestones
| 11-Sep-2015 | Project Brief Complete |
| 25-Sep-2015 | Foundation Stage Complete - Framework Developed |
| 30-Oct-2015 | View Only Student Hub Complete |
| 09-Nov-2015 | Deliver View Only Hub (Limited set of users) |
| 15-Jan-2016 | Update Student Hub Complete |
| 21-Jan-2016 | Deploy to Live |
| 19-Feb-2016 | DSOR Sign Off |
| 04-Mar-2016 | Closure |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days