Project Status Reports

Title Report Date Time Cost Scope Overall Change
January 2016 January 2016 BLUE
November 2015 November 2015 AMBER GREEN GREEN AMBER
October 2015 October 2015 AMBER GREEN GREEN AMBER
September 2015 September 2015 GREEN GREEN GREEN GREEN

Project Info

Project
Path enhancements for pre-applicants/enquirers
Code
SAC045
Programme
Student Systems Partnership SSP
Project Manager
Andrew Crossland
Project Sponsor
Lisa Dawson
Current Stage
Initiate
Status
Withdrawn
Start Date
13-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jan-2016
Programme Priority
3
Overall Priority
Normal
Category
Discretionary

Documentation