July 2016

Report Date
July 2016

Achievements

  • SITS build complete; testing nearing completion
  • BIS Evasys universe build complete; testing in progress
  • BIS STUDMI and Programmes universes build complete; teting nearing completion
  • Data architecture build complete in all environments
  • Dashboards homepage built within 'Data Matters' area of Staff website
  • Sample dashboard published with staff-level security applied via EASE
  • Web services security issues solved; load testing in progress

 

Open Issues

  • SITS delays caused by prioritisation of SAC050, Annual Review, and EUCLID performance issues; this, along with outstanding BIS rework and dependency on SAC050 mean implementation delayed to 15/8,possibly 22/8

 

Resolved Issues

  • Dashboard publication on secure https page
  • Web Services security issues
  • EASE-protection and staff access restriction

 

Next Steps

  • Complete SITS/BIS re-work and testing
  • Deploy IS strands to Live
  • Continue dashboard/Webi build
  • Develop publicity materials

 

15-Aug-2016Deploy IS Strands to Live
07-Oct-2016Build Dashboards completed
28-Oct-2016Test Dashboards completed
31-Oct-2016Deploy Dashboards to Live
22-Nov-2016Deployment Sign off Review
09-Dec-2016Close
Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Use of Student Data: Dashboards
Code
SAC044
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Jamie Morton
Project Sponsor
Barry Neilson
Current Stage
Close
Status
Closed
Start Date
13-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
14-Apr-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary