June 2016
- Report Date
- June 2016
Achievements
- SITS developments first iteration complete and undergoing testing
- Revised requirements for Evasys data capture agreed and in development
- Data architecture build complete
- Data capture and transfer build complete
- BIS build nearing completion
- Dashboard skills handover from Dufrain complete
- Meeting with Records Management undertaken
Open Issues
- None
Resolved Issues
- None
Next Steps
- Complete SITS build and test
- Complete BIS build and test
- Commence dashboard/Webi build
27-Jun-2016 | Sign off build BIS Universes |
14-Jul-2016 | Sign off build Data Architecture, data capture and transfer |
14-Jul-2016 | Sign off build SITS changes |
28-Jul-2016 | Test Sign off: Data Transfer and Capture, and BIS |
01-Aug-2016 | Deploy IS Strands to Live |
07-Oct-2016 | Build Dashboards completed |
28-Oct-2016 | Test Dashboards completed |
31-Oct-2016 | Deploy Dashboards to Live |
22-Nov-2016 | Deployment Sign off Review |
09-Dec-2016 | Close |
- Approved budget
- 194.0 days
- Activity this month
- 50.0 days
- Activity this year
- 109.0 days
- Activity to date
- 109.0 days
- Estimate to complete current year
- 49.0 days
- Estimate to complete future years
- 16.0 days