Achievements

  • SITS developments first iteration complete and undergoing testing
  • Revised requirements for Evasys data capture agreed and in development
  • Data architecture build complete
  • Data capture and transfer build complete
  • BIS build nearing completion
  • Dashboard skills handover from Dufrain complete
  • Meeting with Records Management undertaken

 

Open Issues

  • None

 

Resolved Issues

  • None

 

Next Steps

  • Complete SITS build and test
  • Complete BIS build and test
  • Commence dashboard/Webi build

 

27-Jun-2016Sign off build BIS Universes
14-Jul-2016Sign off build Data Architecture, data capture and transfer
14-Jul-2016Sign off build SITS changes
28-Jul-2016Test Sign off: Data Transfer and Capture, and BIS
01-Aug-2016Deploy IS Strands to Live
07-Oct-2016Build Dashboards completed
28-Oct-2016Test Dashboards completed
31-Oct-2016Deploy Dashboards to Live
22-Nov-2016Deployment Sign off Review
09-Dec-2016Close
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
194.0 days
Activity this month
50.0 days
Activity this year
109.0 days
Activity to date
109.0 days
Estimate to complete current year
49.0 days
Estimate to complete future years
16.0 days

Project Info

Project
Use of Student Data: Dashboards
Code
SAC044
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Jamie Morton
Project Sponsor
Barry Neilson
Current Stage
Close
Status
Closed
Start Date
13-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
14-Apr-2017
Programme Priority
2
Overall Priority
Normal
Category