End of March 2016

Report Date
March 2016

Achievements

  • ADA drafted and reviewed

Resolved Issues

N/A

Open Issues

Next Steps

  • Steering Group 7/4/16: Agree high level deliverables & use of resources
  • Finalise ADA, deliver SDS, revise project brief accordingly
  • Deliver user stories
  • User workshops

 

06-May-2016End of planning
Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
RED
Overall
RED
Change Status
Activity
Approved budget
50.0 days
Activity this month
5.0 days
Activity this year
9.0 days
Activity to date
9.0 days
Estimate to complete current year
41.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Use of Student Data: Dashboards
Code
SAC044
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Jamie Morton
Project Sponsor
Barry Neilson
Current Stage
Close
Status
Closed
Start Date
13-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
14-Apr-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary