January 2017

Report Date
January 2017

Achievements last period

  • Course Evaluation publication security issues resolved
  • Course Evaluation staff reports successfully published
  • Course Evaluation college and school reports built and signed off for publication
  • All project work complete
  • Any potential improvements/rework identified so far have been logged for future reference

Open Issues

Resolved Issues

  • Project is over budget and new budget needs to be approved

Next Steps

  • Close project

RAG Status

Amber - additional budget approved

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
263.0 days
Activity this month
0.0 days
Activity this year
87.0 days
Activity to date
257.0 days
Estimate to complete current year
6.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Use of Student Data: Dashboards
Code
SAC044
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Jamie Morton
Project Sponsor
Barry Neilson
Current Stage
Close
Status
Closed
Start Date
13-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
14-Apr-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary