November 2016
- Report Date
- November 2016
Achievements last period
- Evasys text responses enabled in Course Evaluation universe
- Further universe changes to handle multi-response questions and revised staff question sets implemented
- Implemented in-house solution to surfacing text responses in BIS universe
- Course Evaluation and NSS survey outcomes published in beta version on 'Data Matters' website
- Automation of two-level dashboard security based on user authorisation implemented
- Google Analytics enabled on dashboards
- Milestones replanned – closure Jan 2017 to cover Course Evaluation semester 1 reporting
- Staff report publication proof of concept undertaken
Open Issues
- Milestones to be replanned
- Capture of live course evaluation survey responses for 2016/7
- Email encryption for staff report publication
Resolved Issues
Next Steps
- Continue dashboard/Webi build
- Explore deeper analytics options
- Agree new milestones and budget
Closure 31/1
- Approved budget
- 220.0 days
- Activity this month
- 9.0 days
- Activity this year
- 60.0 days
- Activity to date
- 229.0 days
- Estimate to complete current year
- 12.0 days
- Estimate to complete future years
- 0.0 days