August 2016
- Report Date
- August 2016
Achievements last period
- SITS build and Programmes universe implemented in LIVE
- BIS Evasys universe testing in progress
- BIS STUDMI ready for implementation (dependency on Evasys universe)
- Content for Dashboards pages in 'Data Matters' website in development
- Solution for restraicting sencitive dashboard to authorised users in development
- Engagement plan circulated for comment
Open Issues
- Outstanding BIS rework of Evasys universe and jury duties delay implementation of STUDMI and underlying STUHUB database developments. Implementation scheduled for w/c 12/9
- Testing of Evasys 'long field' and (new scope) development of security mechanism for authorised staff impacted by jury service.
- New scope: requirement identified for hosting on AT in addition to KB to support Disaster Recovery: solution in progress.
- Revised milestones and budget detailed in piccl https://www.projects.ed.ac.uk/project/sac044/issues/14
Resolved Issues
- CSV Connector procured & Web Services performance issues resolved through use of Alteryx (licences funded): give much more streamlined, automated and sustainable methods for transforming the data and supplying it to the dashboards
- EASE-protection and staff access restriction
Next Steps
- Complete BIS re-work and implementation
- Continue dashboard/Webi build
- Finalise and publish publicity materials
- Complete long field and security developments
12-Sep-2016 Deploy IS Strands to Live 07-Oct-2016 Build Dashboards completed 28-Oct-2016 Test Dashboards completed 31-Oct-2016 Deploy Dashboards to Live 22-Nov-2016 Deployment Sign off Review 09-Dec-2016 Close
- Approved budget
- 220.0 days
- Activity this month
- 29.0 days
- Activity this year
- 29.0 days
- Activity to date
- 198.0 days
- Estimate to complete current year
- 26.0 days
- Estimate to complete future years
- 0.0 days