Report for July 2015

Report Date
July 2015

Achievements in last period

  • Testing complete all issues resolved
  • Deployment Annual Review Form Complete
  • Roadshow Events Scheduled

Issues

  • n/a

Next Steps

  • Project will not be closed until subsequent phases are delivered.
  • Estimate and Plan next phase of the project
  • Redefine scope of deliverable get agreement from Student Systems Director.
  • Confirm Milestones below are indicative.

 

28-Sep-2015PPMD -> EUCLID Build Complete
16-Oct-2015PPMD -> EUCLID - Acceptance Sign-Off
28-Oct-2015PPMD -> EUCLID Deploy to Live
27-Nov-2015Deployment Sign-Off
01-Dec-2015Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
172.0 days
Activity this month
11.0 days
Activity this year
77.0 days
Activity to date
77.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
96.0 days

Project Info

Project
Postgraduate Research - Student Life Cycle
Code
SAC041
Programme
Student Systems Partnership SSP
Project Manager
Ruth McCallum
Project Sponsor
Jeremy Bradshaw
Current Stage
Close
Status
Closed
Start Date
01-Oct-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
18-Sep-2015
Programme Priority
2
Overall Priority
Normal
Category
Discretionary

Documentation