Report for July 2015
- Report Date
- July 2015
Achievements in last period
- Testing complete all issues resolved
- Deployment Annual Review Form Complete
- Roadshow Events Scheduled
Issues
- n/a
Next Steps
- Project will not be closed until subsequent phases are delivered.
- Estimate and Plan next phase of the project
- Redefine scope of deliverable get agreement from Student Systems Director.
- Confirm Milestones below are indicative.
| 28-Sep-2015 | PPMD -> EUCLID Build Complete |
| 16-Oct-2015 | PPMD -> EUCLID - Acceptance Sign-Off |
| 28-Oct-2015 | PPMD -> EUCLID Deploy to Live |
| 27-Nov-2015 | Deployment Sign-Off |
| 01-Dec-2015 | Closure |
- Approved budget
- 172.0 days
- Activity this month
- 11.0 days
- Activity this year
- 77.0 days
- Activity to date
- 77.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 96.0 days