July project report

Report Date
July 2014
Achievements in Last Period
  • July release deployed: Included improvements to general functionality of paperless, a number of bug fixes and review and deployment of the layout of mutiple key screens in preparation for the September release

Issues

n/a

Next Steps

  • Development of September release user stories
  • Halfway review of September release with user group

 

Target dateTitle
19-Sep-2014Acceptance sign-off milestone (release 2)
23-Sep-2014Release 2
27-Oct-2014Deployment sign off review DSOR
07-Nov-2014Close  

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
180.0 days
Activity this month
26.0 days
Activity this year
71.0 days
Activity to date
71.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
73.0 days

Project Info

Project
UCAS Paperless Admission Phase 2
Code
SAC031
Programme
Student Systems Partnership SSP
Project Manager
Ruth McCallum
Project Sponsor
Rebecca Gaukroger
Current Stage
Close
Status
Closed
Start Date
11-Mar-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
16-Jan-2015
Programme Priority
2
Category
Discretionary

Documentation