July project report
- Report Date
- July 2014
Achievements in Last Period
- July release deployed: Included improvements to general functionality of paperless, a number of bug fixes and review and deployment of the layout of mutiple key screens in preparation for the September release
Issues
n/a
Next Steps
- Development of September release user stories
- Halfway review of September release with user group
| Target date | Title |
|---|---|
| 19-Sep-2014 | Acceptance sign-off milestone (release 2) |
| 23-Sep-2014 | Release 2 |
| 27-Oct-2014 | Deployment sign off review DSOR |
| 07-Nov-2014 | Close |
- Approved budget
- 180.0 days
- Activity this month
- 26.0 days
- Activity this year
- 71.0 days
- Activity to date
- 71.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 73.0 days