March project update
- Report Date
- March 2014
Achievements in Last Period
- Scope of changes assessed from a technical standpoint
- Refinement of issues and priorities
Issues
- Lack of resource, key developer is tasked with an urgent task and isn't available to start work on this project yet
- Inexperienced resource, with Helen leaving Paul and Greg have been assigned to this project but neither have any SITS experience
- Debate on whether to include technological advances into paperless admissions or just stick to enhancing the software via user stories. Meeting to discuss arranged
Next Steps
- Finalise priorites and first sprint
- Review technological advances and senior management to make a decision on if they will be implemented or not
- Approved budget
- 120.0 days
- Activity this month
- 0.6 days
- Activity this year
- 3.1 days
- Activity to date
- 3.1 days
- Estimate to complete current year
- 70.0 days
- Estimate to complete future years
- 50.0 days