Report for September 2014

Report Date
September 2014

Achievements in Last Period

  • Tribal Form signed-off
  • Tribal form delivered to LIve

Issues

N/a

Next Steps   

  • Complete handover to Applications Mangement
  • Close Project

 

31/10/14 Close Project

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
30.0 days
Activity this month
0.2 days
Activity this year
0.5 days
Activity to date
26.5 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Project
Implement Tribal FAQ System
Code
SAC029
Programme
Student Systems Partnership SSP
Project Manager
Ruth McCallum
Project Sponsor
Niall Bradley
Current Stage
Close
Status
Closed
Start Date
06-Jan-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
14-Nov-2014
Programme Priority
2
Category
Discretionary