Report for June 2014
- Report Date
- June 2014
Achievements in last period
- Testing HEAR document students
- Build and test of HEAR from EUCLID HEAR page
- Produced framework for production of other student documents within EUCLID student view
Issues
- StuTalk still an issue, this is required for Release 2 only - latest consultancy revealed bug in software, see Bug in StuTalk.
Next Steps
- Complete integration testing of HEAR
- Build other student documents in EUCLID
- Integration testing of other student documents
- UAT of HEAR and other documents
Milestones
| Target date | Title |
|---|---|
| 04-Aug-2014 | Acceptance sign off - Release 1 |
| 12-Aug-2014 | Release 1 Delivery |
| 21-Aug-2014 | Acceptance sign off - Release 2 |
| 02-Sep-2014 | Release 2 Delivery |
| 25-Sep-2014 | Deployment Sign off |
| 26-Sep-2014 | Project close |
- Approved budget
- 140.0 days
- Activity this month
- 31.8 days
- Activity this year
- 108.7 days
- Activity to date
- 108.7 days
- Estimate to complete current year
- 17.4 days
- Estimate to complete future years
- 12.0 days