Report for June 2014

Report Date
June 2014
Achievements in last period
  • Testing HEAR document students 
  • Build and test of HEAR from  EUCLID HEAR page 
  • Produced framework for production of other student documents within EUCLID student view  

 

Issues

  • StuTalk still an issue, this is required for Release 2 only - latest consultancy revealed bug in software, see Bug in StuTalk

 

Next Steps

  • Complete integration testing of  HEAR
  • Build other student documents in EUCLID
  • Integration testing of other student documents
  • UAT of HEAR and other documents

 

Milestones

 

Target dateTitle
04-Aug-2014Acceptance sign off - Release 1
12-Aug-2014Release 1 Delivery
21-Aug-2014Acceptance sign off - Release 2
02-Sep-2014Release 2 Delivery
25-Sep-2014Deployment Sign off
26-Sep-2014Project close

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
140.0 days
Activity this month
31.8 days
Activity this year
108.7 days
Activity to date
108.7 days
Estimate to complete current year
17.4 days
Estimate to complete future years
12.0 days

Project Info

Project
Student Self Service Phase 2
Code
SAC025
Programme
Student Systems Partnership SSP
Project Manager
Chris Giles
Project Sponsor
Craig Shearer
Current Stage
Close
Status
Closed
Start Date
20-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
28-Feb-2015
Programme Priority
1
Overall Priority
Higher
Category
Discretionary