Report for May 2014
- Report Date
- May 2014
Achievements in last period
- Development of single sign on link and end-to-end process of distribution of HEAR from within EUCLID and viewing by recipient (see issue Decision to use single sign on instead of PDF...)
- Well received demo of development version to project sponsor and Student Administration team members
Issues
- Decision was made by project sponsor to delay implementation of all processing until August. (See Go/No go decision for release of HEAR to students this year). Consequently key milestone dates have moved (see Revision to delivery dates) and as a result re-estimation will be complete w/c 9/6. It is very likely this will take the project above agreed 120 day budget (see issue 13 Revised estimates)
- New plan for carry over to be confirmed after re-estimation. Carried over into next year will be deployment of all requirements including Alumni post-live support.
Next Steps
- Complete build and test of HEAR processing from within EUCLID
- Develop and test other documents content
- Develop process to allow other documents to be requested/distributed for students from within EUCLID
| Target date | Title |
|---|---|
| 28-Jul-2014 | Acceptance sign off |
| 05-Aug-2014 | Release 1 Delivery |
| 25-Sep-2014 | Deployment Sign off |
| 26-Sep-2014 | Project close |
- Approved budget
- 120.0 days
- Activity this month
- 15.5 days
- Activity this year
- 76.6 days
- Activity to date
- 76.6 days
- Estimate to complete current year
- 50.0 days
- Estimate to complete future years
- 10.0 days