Report for April 2014

Report Date
April 2014
Achievements in last period
  • Refined user stories for HEAR docuement to reflect changes
  • Further development of HEAR document and process to produce pdf.

 

Issues

  • Conflicting project priorities has meant that little progress has been made on the project.  This has resulted in re-plannign of first implementation: see issue Change to first implementation date and content
  • Difficulties implementing StuTalk.  The Alumni implementation that relies on StuTalk has been removed from first implementation.

 

Next Steps

 

Target dateTitle
29-May-2014Go/No go decision for release of HEAR to students this year
26-Jun-2014Release 1 Delivery
23-Jul-2014Release 2 Delivery
06-Aug-2014Deployment Sign off
13-Aug-2014Project close

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
AMBER
Overall
AMBER
Change Status
Activity
Approved budget
120.0 days
Activity this month
7.9 days
Activity this year
61.2 days
Activity to date
61.2 days
Estimate to complete current year
51.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Student Self Service Phase 2
Code
SAC025
Programme
Student Systems Partnership SSP
Project Manager
Chris Giles
Project Sponsor
Craig Shearer
Current Stage
Close
Status
Closed
Start Date
20-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
28-Feb-2015
Programme Priority
1
Overall Priority
Higher
Category
Discretionary