Report for April 2014
- Report Date
- April 2014
Achievements in last period
- Refined user stories for HEAR docuement to reflect changes
- Further development of HEAR document and process to produce pdf.
Issues
- Conflicting project priorities has meant that little progress has been made on the project. This has resulted in re-plannign of first implementation: see issue Change to first implementation date and content
- Difficulties implementing StuTalk. The Alumni implementation that relies on StuTalk has been removed from first implementation.
Next Steps
- Incoporate prototype into current HEAR page
- Set up PDF certification infrastructure
- Go/No-go checkpoint at end of May (see issue Change to first implementation date and content)
| Target date | Title |
|---|---|
| 29-May-2014 | Go/No go decision for release of HEAR to students this year |
| 26-Jun-2014 | Release 1 Delivery |
| 23-Jul-2014 | Release 2 Delivery |
| 06-Aug-2014 | Deployment Sign off |
| 13-Aug-2014 | Project close |
- Approved budget
- 120.0 days
- Activity this month
- 7.9 days
- Activity this year
- 61.2 days
- Activity to date
- 61.2 days
- Estimate to complete current year
- 51.5 days
- Estimate to complete future years
- 0.0 days