Report for February 2014

Report Date
February 2014
Achievements in last period
  • Built end-to-end process for existing HEAR HTML SRL to convert to pdf and digitally signed 

 

Issues

  • Continued conflicting priorities have meant that the PM/BA  did not complete the iteration planning. Agreed with SSP Management that another analyst would take over PM duties on return from sick leave mid March.  See https://www.projects.ed.ac.uk/project/sac025/issues/7

 

Next Steps

  • Estimate and plan future iterations
  • Build integration test end to end process for production of HEAR for Alumni 

 

Milestones

Target dateTitle
13-Mar-2014End of Foundations
06-May-2014Priority 1 Requirements Delivery
03-Jun-2014Priority 2 Requirements Delivery
15-Jul-2014Deployment Sign off
31-Jul-2014Project close

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
120.0 days
Activity this month
11.6 days
Activity this year
38.6 days
Activity to date
38.6 days
Estimate to complete current year
82.2 days
Estimate to complete future years
0.0 days

Project Info

Project
Student Self Service Phase 2
Code
SAC025
Programme
Student Systems Partnership SSP
Project Manager
Chris Giles
Project Sponsor
Craig Shearer
Current Stage
Close
Status
Closed
Start Date
20-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
28-Feb-2015
Programme Priority
1
Overall Priority
Higher
Category
Discretionary