Report for February 2014
- Report Date
- February 2014
Achievements in last period
- Built end-to-end process for existing HEAR HTML SRL to convert to pdf and digitally signed
Issues
- Continued conflicting priorities have meant that the PM/BA did not complete the iteration planning. Agreed with SSP Management that another analyst would take over PM duties on return from sick leave mid March. See https://www.projects.ed.ac.uk/project/sac025/issues/7
Next Steps
- Estimate and plan future iterations
- Build integration test end to end process for production of HEAR for Alumni
Milestones
| Target date | Title |
|---|---|
| 13-Mar-2014 | End of Foundations |
| 06-May-2014 | Priority 1 Requirements Delivery |
| 03-Jun-2014 | Priority 2 Requirements Delivery |
| 15-Jul-2014 | Deployment Sign off |
| 31-Jul-2014 | Project close |
- Approved budget
- 120.0 days
- Activity this month
- 11.6 days
- Activity this year
- 38.6 days
- Activity to date
- 38.6 days
- Estimate to complete current year
- 82.2 days
- Estimate to complete future years
- 0.0 days