December 2013
- Report Date
- December 2013
Achievements in last period
- Completion of report on proposed method of producing secure document
Issues
- Brief was not signed off as planned and proposed document approach not presented to sponsor . See issue https://www.projects.ed.ac.uk/project/sac025/issues/4
Next Steps
- Present document provision proposal to sponsor (completed 9/1/14)
- Sign off brief (submitted to WIS 9/1/14)
- Investigate pdf production following SITS 8.7.0 upgrade to DEV
- Definition and prioritisation of requirements
- Estimate and plan project
| Target date | Title |
|---|---|
| 10-Jan-2014 | Complete intial prototyping/design |
| 17-Jan-2014 | Project Planning/Prioritisation Complete |
| 01-Apr-2014 | Priority 1 Requirements Delivery |
| 03-Jun-2014 | Priority 2 Requirements Delivery |
| 15-Jul-2014 | Deployment Sign off |
| 31-Jul-2014 | Project close |
- Approved budget
- 120.0 days
- Activity this month
- 3.0 days
- Activity this year
- 17.9 days
- Activity to date
- 17.9 days
- Estimate to complete current year
- 102.0 days
- Estimate to complete future years
- 0.0 days