Report for November 2013
- Report Date
- November 2013
Achievements in last period
- Work progressing on document verication proposal/prototype
Issues
- IS SSP resource not available to complete proposal/for document verification as planned. (See issue 3)
- Following re-organisation of Academic Registry, agreement has not been reached on scope so brief was not signed off as planned. (See issue 3)
Next Steps
- Gain agreement on scope
- Sign off brief
- Complete proposal/prototype and gain agreement on approach
| Target date | Title |
|---|---|
| 06-Dec-2013 | Complete intial prototyping/design |
| 13-Dec-2013 | Project Brief signed off |
| 17-Jan-2014 | Project Planning/Prioritisation Complete |
- Approved budget
- 120.0 days
- Activity this month
- 2.0 days
- Activity this year
- 15.0 days
- Activity to date
- 15.0 days
- Estimate to complete current year
- 115.0 days
- Estimate to complete future years
- 0.0 days