Report for November 2013

Report Date
November 2013
Achievements in last period
  • Work progressing on document verication proposal/prototype

Issues

  • IS SSP resource not available to complete proposal/for document verification as planned. (See issue 3)
  • Following re-organisation of Academic Registry, agreement has not been reached on scope so brief was not signed off as planned. (See issue 3)

Next Steps

  • Gain agreement on scope
  • Sign off brief
  • Complete proposal/prototype and gain agreement on approach
Target dateTitle
06-Dec-2013Complete intial prototyping/design
13-Dec-2013Project Brief signed off
17-Jan-2014Project Planning/Prioritisation Complete

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
AMBER
Overall
AMBER
Change Status
Activity
Approved budget
120.0 days
Activity this month
2.0 days
Activity this year
15.0 days
Activity to date
15.0 days
Estimate to complete current year
115.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Student Self Service Phase 2
Code
SAC025
Programme
Student Systems Partnership SSP
Project Manager
Chris Giles
Project Sponsor
Craig Shearer
Current Stage
Close
Status
Closed
Start Date
20-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
28-Feb-2015
Programme Priority
1
Overall Priority
Higher
Category
Discretionary