Report for October 2013

Report Date
October 2013
Achievements in last period
  • Internal sign off of brief

Issues

  • Meeting to sign off brief with Sponsor delayed,  scope is under review. 
  • IS SSP resource not available to produce prototype for document verification as planned.

Next Steps

  • Sign off brief
  • Develop prototype 
  • Complete Initial estimates/planning
  • Analysis

Milestones

Target dateTitle
12-Nov-2013Project Brief signed off
20-Nov-2013Complete intial prototyping/design
30-Nov-2013Project Planning/Prioritisation Complete

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
120.0 days
Activity this month
2.8 days
Activity this year
12.4 days
Activity to date
12.4 days
Estimate to complete current year
107.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Student Self Service Phase 2
Code
SAC025
Programme
Student Systems Partnership SSP
Project Manager
Chris Giles
Project Sponsor
Craig Shearer
Current Stage
Close
Status
Closed
Start Date
20-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
28-Feb-2015
Programme Priority
1
Overall Priority
Higher
Category
Discretionary