Report for October 2013
- Report Date
- October 2013
Achievements in last period
- Internal sign off of brief
Issues
- Meeting to sign off brief with Sponsor delayed, scope is under review.
- IS SSP resource not available to produce prototype for document verification as planned.
Next Steps
- Sign off brief
- Develop prototype
- Complete Initial estimates/planning
- Analysis
Milestones
| Target date | Title |
|---|---|
| 12-Nov-2013 | Project Brief signed off |
| 20-Nov-2013 | Complete intial prototyping/design |
| 30-Nov-2013 | Project Planning/Prioritisation Complete |
- Approved budget
- 120.0 days
- Activity this month
- 2.8 days
- Activity this year
- 12.4 days
- Activity to date
- 12.4 days
- Estimate to complete current year
- 107.0 days
- Estimate to complete future years
- 0.0 days