Report for November 2014

Report Date
November 2014
Achievements in last period
  • Academic statement successfully used in production. Student have accessed the Academic statement on 341 occasions since 31 October.
  • Met with Sponsor who has considered the project a success - Student Information Point have received very few queries and students have produced a total of  4700  documents up to 2 December.  

 

Issues

  • Alumni portal link has not been deployed to TEST due to BA not obtaining sign off from business - delayed to 20 November, see https://www.projects.ed.ac.uk/project/sac025/issues/21, with a knock on delay to project closure date. (Note that alumni can access the relevant documents directly from the Student Administration  website - the Alumni channel is simply another route to the documents)

 

Next Steps

  • Sign off of Alumni Portal portlet
  • Deployment of Alumni Portal portlet
  • Project close

 

Milestones

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
157.0 days
Activity this month
0.3 days
Activity this year
20.8 days
Activity to date
147.2 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Project
Student Self Service Phase 2
Code
SAC025
Programme
Student Systems Partnership SSP
Project Manager
Chris Giles
Project Sponsor
Craig Shearer
Current Stage
Close
Status
Closed
Start Date
20-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
28-Feb-2015
Programme Priority
1
Overall Priority
Higher
Category
Discretionary