Report for September 2014

Report Date
September 2014
Achievements in last period
  • Deployment of post go live fixes/enhancements
  • Development of Academic statement (build)
  • Short term solution devised for Alumni access through MyEd

 

Issues

 

Next Steps

  • Development of simple Alumni portal link
  • Test academic statement
  • Deployment of phase 2

 

Milestones

Target datePrevious dateTitle
24-Oct-201418-Sep-2014Acceptance sign off - Release 2
30-Oct-201430-Sep-2014Release 2 Delivery
07-Nov-201425-Sep-2014Deployment Sign off
13-Nov-201424-Oct-2014Project close

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
157.0 days
Activity this month
0.6 days
Activity this year
16.5 days
Activity to date
142.9 days
Estimate to complete current year
16.6 days
Estimate to complete future years
0.0 days

Project Info

Project
Student Self Service Phase 2
Code
SAC025
Programme
Student Systems Partnership SSP
Project Manager
Chris Giles
Project Sponsor
Craig Shearer
Current Stage
Close
Status
Closed
Start Date
20-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
28-Feb-2015
Programme Priority
1
Overall Priority
Higher
Category
Discretionary