Report for September 2014
- Report Date
- September 2014
Achievements in last period
- Deployment of post go live fixes/enhancements
- Development of Academic statement (build)
- Short term solution devised for Alumni access through MyEd
Issues
- StuTalk solution was not progressed, further Tribal consultancy booked: see update to Risk to Phase 2 delivery via StuTalk through Alumni MyEd
Next Steps
- Development of simple Alumni portal link
- Test academic statement
- Deployment of phase 2
Milestones
| Target date | Previous date | Title |
|---|---|---|
| 24-Oct-2014 | 18-Sep-2014 | Acceptance sign off - Release 2 |
| 30-Oct-2014 | 30-Sep-2014 | Release 2 Delivery |
| 07-Nov-2014 | 25-Sep-2014 | Deployment Sign off |
| 13-Nov-2014 | 24-Oct-2014 | Project close |
- Approved budget
- 157.0 days
- Activity this month
- 0.6 days
- Activity this year
- 16.5 days
- Activity to date
- 142.9 days
- Estimate to complete current year
- 16.6 days
- Estimate to complete future years
- 0.0 days