Report for August 2014
- Report Date
- August 2014
Achievements in last period
- User acceptance
- Walkthrough of configuration of IS Apps Management
- Deployment of of HEAR and other documents to LIVE
- Post-go Live maintenance
- 230 documents requested by students in first 2 weeks
Issues
- There is a risk to delivery of the Alumni Portal for the end of September. The documents will be available for Alumni, but not necessarily using StuTalk. See Risk to Phase 2 delivery via StuTalk through Alumni MyEd
Next Steps
- Development of Academic statement document for Alumni
- Develop access to HEAR and Academic Statement for Alumni
- Develop access from Alunmi MyEd portal
- Post go live maintenance - fixes/enhancements
Milestones
| Target date | Title | Complete |
|---|---|---|
| 18-Sep-2014 | Acceptance sign off - Release 2 | No |
| 30-Sep-2014 | Release 2 Delivery | No |
| 24-Oct-2014 | Deployment Sign off | No |
| 24-Oct-2014 | Project close | No |
- Approved budget
- 157.0 days
- Activity this month
- 12.0 days
- Activity this year
- 12.0 days
- Activity to date
- 138.4 days
- Estimate to complete current year
- 18.9 days
- Estimate to complete future years
- 0.0 days