Report for July 2014
- Report Date
- July 2014
Achievements in last period
- Development and test of other student documents in EUCLID
- Development and test of staff functions
- StuTalk fix delivered by Tribal (see Bug in StuTalk).
- Issues
None
Next Steps
- Acceptance for release 1
- Deployment release 1
- Development of Alumni functions using StuTalk
Milestones
| Target date | Title |
|---|---|
| 04-Aug-2014 | Acceptance sign off - Release 1 |
| 12-Aug-2014 | Release 1 Delivery |
| 21-Aug-2014 | Acceptance sign off - Release 2 |
| 02-Sep-2014 | Release 2 Delivery |
| 25-Sep-2014 | Deployment Sign off |
| 26-Sep-2014 | Project close |
- Approved budget
- 140.0 days
- Activity this month
- 18.0 days
- Activity this year
- 126.0 days
- Activity to date
- 126.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 14.0 days