Report for September 2013

Report Date
September 2013

Achievements in last period

  • Draft brief
  • Initial discussions of scope/content with project sponsor
  • Initial prototypes of HEAR pages

Issues

  •  

Next Steps

  • Sign off of brief
  • Complete Initial estimates/planning
  • Start protoptyping documents on demand.

Milestones

Target dateTitle
11-Oct-2013Project Brief signed off
01-Nov-2013Project Planning/Prioritisation Complete

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
120.0 days
Activity this month
0.3 days
Activity this year
9.6 days
Activity to date
9.6 days
Estimate to complete current year
110.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Student Self Service Phase 2
Code
SAC025
Programme
Student Systems Partnership SSP
Project Manager
Chris Giles
Project Sponsor
Craig Shearer
Current Stage
Close
Status
Closed
Start Date
20-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
28-Feb-2015
Programme Priority
1
Overall Priority
Higher
Category
Discretionary