Report for September 2013
- Report Date
- September 2013
Achievements in last period
- Draft brief
- Initial discussions of scope/content with project sponsor
- Initial prototypes of HEAR pages
Issues
Next Steps
- Sign off of brief
- Complete Initial estimates/planning
- Start protoptyping documents on demand.
Milestones
| Target date | Title |
|---|---|
| 11-Oct-2013 | Project Brief signed off |
| 01-Nov-2013 | Project Planning/Prioritisation Complete |
- Approved budget
- 120.0 days
- Activity this month
- 0.3 days
- Activity this year
- 9.6 days
- Activity to date
- 9.6 days
- Estimate to complete current year
- 110.0 days
- Estimate to complete future years
- 0.0 days