August 2013

Report Date
August 2013

Achievements in Last Period

  • Project Opened and Brief being reviewed

Issues

  • N/A

Next Steps

  • Brief sign off.

Milestones

19-Sep-2013Brief completed
02-Oct-2013Refresh DEV from LIVE completed
08-Oct-2013Refresh TEST from LIVE completed
05-Nov-2013Refresh TRN from LIVE completed
06-Dec-2013Upgrade DEV to 8.7.0 completed
19-Dec-2013Testing upgrade to DEV reviewed
10-Jan-2014Upgrade TEST to 8.7.0 completed
14-Feb-2014Acceptance Review ASOR
03-Mar-2014Upgrade LIVE to v8.7.0 completed
17-Mar-2014Second Refresh of TEST from LIVE completed
17-Mar-2014LIVE Deployment review 1
31-Mar-2014Upgrade TRN to v8.7.0 completed
14-Apr-2014Deployment review 2
28-Apr-2014Close

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
150.0 days
Activity this month
1.4 days
Activity this year
1.4 days
Activity to date
1.4 days
Estimate to complete current year
148.0 days
Estimate to complete future years
0.0 days

Project Info

Project
SITS Upgrade
Code
SAC024
Programme
Student Systems Partnership SSP
Project Manager
Franck Bergeret
Project Sponsor
Karen Osterburg
Current Stage
Close
Status
Closed
Start Date
20-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
11-Jul-2014
Programme Priority
2
Overall Priority
Normal
Category
Compliance