Report for January 2013

Report Date
January 2013

 

Achievements in Last Period

  • Acceptance sign off ASOR
  • Live deployment
  • Deployment sign off DSOR

Issues

  • n/a

Next Steps  

  • TRN reconfiguration
  • Close project

 

 

Target dateTitle
22-Feb-2013Close

 

 

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
51.0 days
Activity this month
15.5 days
Activity this year
46.9 days
Activity to date
46.9 days
Estimate to complete current year
4.1 days
Estimate to complete future years
0.0 days

Project Info

Project
Retirement of EUCLID Web Servers
Code
SAC013
Programme
Student Systems Partnership SSP
Project Manager
Franck Bergeret
Project Sponsor
Karen Osterburg
Current Stage
Close
Status
Closed
Start Date
22-Aug-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
15-Mar-2013
Programme Priority
5
Overall Priority
Normal
Category
Compliance