Report for January 2020

Report Date
January 2020

Project on hold due to RSS Resource availability to fully engage on the Project due to other commitments

Suspended until Apr 20

 

Achievements in Last Period

  • Month End Suspended Reporting

Issues and Risks

Open issues currently impacting on the project timeline, budget or scope:

  • N/A

Any current or imminent risks that need to be managed:

  • Project Delivery - Due to lack of Resources/BAU

Next Steps

  • Allocate Resource time to fully engage on Project
  • Detailed planning meeting with each 3rd Party
  • Produce Project plan
  • Complete Project Brief 

Future Milestones

**********Detailed Planning Still to take place Dates TBC**********

           Milestone

   Date of Milestone  

  1.  Start Project            

           02 Sep 19

  2.  Planning Date         

           20 Dec 19

  3.  Delivery Date 1

           19 Jun 20 

  4.  Close Project Date         

           03 Jul 20

 

GUIDE TO RAG STATUS : project_planning_-_guide_to_rag_status.docx

Project Sponsor Commentary / Approval

- Approved

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
-Project Suspended due to no RSS Resource availability to fully engage on the Project due to other commitments -Suspended until Apr 20
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
Yes
Escalated to
Escalated to Project Sponsor and Programme Manager
Change Commentary
-Project Suspended due to no RSS Resource availability to fully engage on the Project due to other commitments -Suspended until Apr 20
Activity
Approved budget
50.0 days
Activity this month
0.5 days
Activity this year
1.3 days
Activity to date
1.3 days
Estimate to complete current year
48.7 days
Estimate to complete future years
0.0 days

Project Info

Project
Future Storage Models
Code
RSS213
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Peter Sanderson
Project Sponsor
David Fergusson
Current Stage
Plan
Status
Suspended
Project Classification
Grow
Start Date
02-Sep-2019
Planning Date
08-Apr-2020
Delivery Date
19-Jun-2020
Close Date
03-Jul-2020
Overall Priority
Normal
Category
Discretionary

Documentation