Report for December 2019
- Report Date
- December 2019
Achievements in Last Period
-
Project brief drafted and under review
-
Project plan revised in line with impact of industrial action (two week slippage)
-
Requirements planning in progress
-
Budget approved for external development resources to work on Retention and UI improvements
Risks/Issues
-
None at present
Next Steps
-
Complete and approve requirements document
-
Update project brief and submit for approval
-
Start design phase
Target Date | Title | Stage | Complete |
---|---|---|---|
10/01/2020 | Requirements planning completed | Plan | No |
24/01/2020 | Project brief/planning completed | Plan | No |
21/02/2020 | Encryption key management options evaluated | Design | No |
21/02/2020 | Overall design work completed | Design | No |
17/04/2020 | Further resilience & recovery in operation | Build | No |
17/04/2020 | Retention date management released | Deliver | No |
17/04/2020 | Implementation of deposits from other file systems completed | Build | No |
12/06/2020 | UI/PURE improvements released | Deliver | No |
12/06/2020 | Performance improvements in operation | Build | No |
10/07/2020 | TSM/Oracle client-side encryption and checksums evaluated | Deliver | No |
27/07/2020 | Project closed | Close | No |
- Approved budget
- 318.0 days
- Activity this month
- 5.5 days
- Activity this year
- 9.0 days
- Activity to date
- 9.0 days
- Estimate to complete current year
- 306.0 days
- Estimate to complete future years
- 0.0 days