Report for November 2019

Report Date
November 2019
Achievements in Last Period
  • Draft plan completed

  • Requirements planning in progress

Risks/Issues

  • Time lost through industrial action

  • External development resources not covered by budget

Next Steps

  • Complete requirements planning

  • Revise outline project plan in line with delay

Target Date Title Stage Complete
10/01/2020 Requirements planning completed Plan No
24/01/2020 Project brief/planning completed Plan No
21/02/2020 Overall design work completed Design No
17/04/2020 Further resilience & recovery in operation Build No
17/04/2020 Retention date management released Deliver No
17/04/2020 Encryption key management improvements in place Build No
12/06/2020 UI/PURE improvements released Deliver No
12/06/2020 Performance improvements in operation Build No
10/07/2020 TSM/Oracle client-side encryption and checksums evaluated Deliver No
27/07/2020 Project closed Close No
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Moderate
Cost
Within Tolerance
Scope
Within Tolerance
Overall
Moderate
Has formal escalation taken place?
No
Change Commentary
Time lost through industrial action; plan revised
Activity
Approved budget
314.0 days
Activity this month
3.5 days
Activity this year
3.5 days
Activity to date
3.5 days
Estimate to complete current year
310.5 days
Estimate to complete future years
0.0 days

Project Info

Project
DataVault Development Phase IV
Code
RSS212
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Lawrence Stevenson
Project Sponsor
Anthony Weir
Current Stage
Plan
Status
In Progress
Project Classification
Grow
Start Date
04-Nov-2019
Planning Date
31-Jan-2020
Delivery Date
19-Jun-2020
Close Date
27-Jul-2020
Overall Priority
Normal
Category
Compliance

Documentation