July 2018

Report Date
July 2018

 

Achievements in Last Period

All nodes have been delivered and tested.

Project closure report has been created, circulated and agreed.

Project Closed.

Issues and Risks

 

Key Tasks For next period

 

 

Milestones

 

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
OpenStack Cloud development
Code
RSS040
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Andy Todd
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Start Date
01-Mar-2018
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Jul-2018
Overall Priority
Normal
Category
Discretionary

Documentation