May 2018

Report Date
May 2018

 

Achievements in Last Period

Order placed. Nodes delivered to Alces. Alces have configured nodes and are ready to deliver, rack and stack, thi sis being held up due to the lack of power.

 

Issues and Risks

Ref Title Initial Risk Current Risk Status Management Approach Risk Owner Date of Last Review  
2 No UPS Capacity at the ACF. RED RED Open Reduce Andy Todd  

view

Key Tasks For next period

 

Agree UPS Requirements with ACF.

Agree how we progress without UPS.

Get delivery dates (from Alces to ACF) and communicate to the ACF.

Plan delivery and installation with the ACF.

 

Milestones

Target Datesort descending Previous Date Title Stage  
08-Jun-2018 No date available Rack and stack (at ACF) Integrate

view

08-Jun-2018 No date available Configure and Integrate Integrate

view

30-Jun-2018 No date available Closure. Close

view

Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
RAG Commentary
Issue - Lack of UPS Availability at the ACF and lack of a way to resolve the issue is impacting commissioning nodes.
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
OpenStack Cloud development
Code
RSS040
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Andy Todd
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Start Date
01-Mar-2018
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Jul-2018