May 2018
- Report Date
- May 2018
Achievements in Last Period
Order placed. Nodes delivered to Alces. Alces have configured nodes and are ready to deliver, rack and stack, thi sis being held up due to the lack of power.
Issues and Risks
Ref | Title | Initial Risk | Current Risk | Status | Management Approach | Risk Owner | Date of Last Review | |
---|---|---|---|---|---|---|---|---|
2 | No UPS Capacity at the ACF. | RED | RED | Open | Reduce | Andy Todd |
Key Tasks For next period
Agree UPS Requirements with ACF.
Agree how we progress without UPS.
Get delivery dates (from Alces to ACF) and communicate to the ACF.
Plan delivery and installation with the ACF.
Milestones
Target Date![]() |
Previous Date | Title | Stage | |
---|---|---|---|---|
08-Jun-2018 | No date available | Rack and stack (at ACF) | Integrate | |
08-Jun-2018 | No date available | Configure and Integrate | Integrate | |
30-Jun-2018 | No date available | Closure. | Close |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days