August report

Report Date
August 2016

RAG Status

Red due to adjusted milestones to allow for re-specification of the HPC storage solution.

Achievements in Last Period

  • No major tasks achieved.
  • Continued to work on the re-specification of storage, providing service where needed in the meantime.

Issues and Risks

  • Resource availability remains fragile
  • Additional storage specification has not yet been defined (Scope: Amber)

Next Steps

  • Complete specification of additional storage component, and adjust scope accordingly or create a separate project for implementing this.
  • Specify and agree final budget assignment and allocate resource accordingly.

 

Future Milestones

 

28-Oct-2016HPC storage tier in service
30-Sep-2016Specification of final spend agreed
31-Oct-2016Final sign off of service provision by project sponsor
Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
RED
Overall
RED
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Roslin Research Computing Expansion
Code
RSS002
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Kenton D'Mellow
Project Sponsor
Alan Archibald
Current Stage
Close
Status
Closed
Start Date
23-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
12-May-2017
Programme Priority
8
Overall Priority
Normal
Category
Discretionary

Documentation