July 2016

Report Date
July 2016

RAG Status

Red due to adjusted milestone for specifying the final allocation of funds.

Achievements in Last Period

  • Nodes have been incorporated in the cluster and are in active service

Issues and Risks

  • Resource availability remains fragile
  • Additional storage specification has not yet been defined (Scope: Amber)

Next Steps

  • Complete specification of additional storage component, and adjust scope accordingly or create a separate project for implementing this.
  • Specify and agree final budget assignment and allocate resource accordingly.

 

Future Milestones

 

31-Aug-2016HPC storage tier in service
31-Aug-2016Specification of final spend agreed
31-Aug-2016Final sign off of service provision by project sponsor
Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
AMBER
Overall
RED
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Roslin Research Computing Expansion
Code
RSS002
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Kenton D'Mellow
Project Sponsor
Alan Archibald
Current Stage
Close
Status
Closed
Start Date
23-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
12-May-2017
Programme Priority
8
Overall Priority
Normal
Category
Discretionary

Documentation