July 2016
- Report Date
- July 2016
RAG Status
Red due to adjusted milestone for specifying the final allocation of funds.
Achievements in Last Period
- Nodes have been incorporated in the cluster and are in active service
Issues and Risks
- Resource availability remains fragile
- Additional storage specification has not yet been defined (Scope: Amber)
Next Steps
- Complete specification of additional storage component, and adjust scope accordingly or create a separate project for implementing this.
- Specify and agree final budget assignment and allocate resource accordingly.
Future Milestones
31-Aug-2016 | HPC storage tier in service |
31-Aug-2016 | Specification of final spend agreed |
31-Aug-2016 | Final sign off of service provision by project sponsor |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days