Progress report
- Report Date
- May 2016
RAG Status
Red due to increased time due to changing scope on the storage infrastructure. However, the project is able to deliver service despite this, using existing available capacity.
Achievements in Last Period
- Final workflow for setting up DataStore allocations created
- design work for network extensions completed
- network extension on-site work with contractors scheduled for June
- backup capacity extensions ordered
- compute nodes connected and burn-in tests complete
Issues and Risks
- Technical work still to be defined, there is a risk this will throw up unknown challenges
- Resource availability remains fragile
- Scope changes due to additional emerging HPC storage requirements
Next Steps
- Backup capacity extensions to be delivered and installed
- Remaining budget spend to be planned out
- Commissioning of compute infrastructure network extension
- Commissioning of compute node extension
- Re-scoping HPC storage solution and implementation plans
Future Milestones
10-Jun-2016 | Network extension completed |
10-Jun-2016 | Compute nodes incorporated in cluster |
31-Aug-2016 | HPC storage tier in service |
30-Jun-2016 | Specification of final spend agreed |
31-Aug-2016 | Final sign off of service provision by project sponsor |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days