Progress report

Report Date
May 2016

RAG Status

Red due to increased time due to changing scope on the storage infrastructure. However, the project is able to deliver service despite this, using existing available capacity.

Achievements in Last Period

  • Final workflow for setting up DataStore allocations created
  • design work for network extensions completed
  • network extension on-site work with contractors scheduled for June
  • backup capacity extensions ordered
  • compute nodes connected and burn-in tests complete

Issues and Risks

  • Technical work still to be defined, there is a risk this will throw up unknown challenges
  • Resource availability remains fragile
  • Scope changes due to additional emerging HPC storage requirements

Next Steps

  • Backup capacity extensions to be delivered and installed
  • Remaining budget spend to be planned out
  • Commissioning of compute infrastructure network extension
  • Commissioning of compute node extension
  • Re-scoping HPC storage solution and implementation plans

 

Future Milestones

 

10-Jun-2016Network extension completed
10-Jun-2016Compute nodes incorporated in cluster
31-Aug-2016HPC storage tier in service
30-Jun-2016Specification of final spend agreed
31-Aug-2016Final sign off of service provision by project sponsor
Project Status
RAG Status
Time
RED
Cost
AMBER
Scope
RED
Overall
RED
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Roslin Research Computing Expansion
Code
RSS002
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Kenton D'Mellow
Project Sponsor
Alan Archibald
Current Stage
Close
Status
Closed
Start Date
23-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
12-May-2017
Programme Priority
8
Overall Priority
Normal
Category
Discretionary

Documentation