April 2016 - Move to final installation
- Report Date
- April 2016
Achievements in Last Period
- Memorandum of Understanding has been agreed and signed off.
- Interim workflow for setting up DataStore allocations defined
- Initial service on compute cluster being granted via existing nodes
- Commissioning of remaining equipment to be scheduled in May
- Backup solution specification obtained
Issues and Risks
- Technical work still to be defined, there is a risk this will throw up unknown challenges
- Resource availability remains fragile
Next Steps
- Backup infrastructure to be ordered and delivered, remaining budget spend to be planned out
- Commissioning of compute infrastructure network extension
- Commissioning of compute node extension, including burn in period
- Commissioning of HPC storage
Future Milestones
31-May-2016 | Compute nodes incorporated in cluster |
31-May-2016 | HPC storage tier in service |
31-May-2016 | Specification of final spend agreed |
30-Jun-2016 | Final sign off of service provision by project sponsor |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days