April 2016 - Move to final installation

Report Date
April 2016

 

Achievements in Last Period

  • Memorandum of Understanding has been agreed and signed off.
  • Interim workflow for setting up DataStore allocations defined
  • Initial service on compute cluster being granted via existing nodes
  • Commissioning of remaining equipment to be scheduled in May
  • Backup solution specification obtained

Issues and Risks

  • Technical work still to be defined, there is a risk this will throw up unknown challenges
  • Resource availability remains fragile

Next Steps

  • Backup infrastructure to be ordered and delivered, remaining budget spend to be planned out
  • Commissioning of compute infrastructure network extension
  • Commissioning of compute node extension, including burn in period
  • Commissioning of HPC storage

 

Future Milestones

 

 

31-May-2016Compute nodes incorporated in cluster
31-May-2016HPC storage tier in service
31-May-2016Specification of final spend agreed
30-Jun-2016Final sign off of service provision by project sponsor

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Roslin Research Computing Expansion
Code
RSS002
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Kenton D'Mellow
Project Sponsor
Alan Archibald
Current Stage
Close
Status
Closed
Start Date
23-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
12-May-2017
Programme Priority
8
Overall Priority
Normal
Category
Discretionary

Documentation