Final installation work to be scheduled
- Report Date
- March 2016
The project sponsor is still reviewing the memorandum of understanding, which has delayed the scheduling of the work to install the HPC equipment and storage.
The DataStore storage equipment has been installed and is now in production. It has not yet been allocated to the groups, but is available when demanded.
Once the sponsor signs off on the MoU, installation is expected to take a total of 4-6 weeks.