Final installation work to be scheduled

Report Date
March 2016

The project sponsor is still reviewing the memorandum of understanding, which has delayed the scheduling of the work to install the HPC equipment and storage.

 

The DataStore storage equipment has been installed and is now in production. It has not yet been allocated to the groups, but is available when demanded.

Once the sponsor signs off on the MoU, installation is expected to take a total of 4-6 weeks.

Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
AMBER
Overall
RED
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Roslin Research Computing Expansion
Code
RSS002
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Kenton D'Mellow
Project Sponsor
Alan Archibald
Current Stage
Close
Status
Closed
Start Date
23-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
12-May-2017
Programme Priority
8
Overall Priority
Normal
Category
Discretionary

Documentation