February 2017

Report Date
February 2017

RAG Status

Amber due to adjusted milestones to allow for delivery of the HPC storage solution.

Achievements in Last Period

  • Purchase Order covering additional HPC storage has been placed.

Issues and Risks

Next Steps

  • delivery/installation of additional storage component.
  • Specify and agree final budget assignment and allocate resource accordingly.

 

Future Milestones

 

28-Oct-2016 HPC storage tier in service
31-Oct-2016 Final sign off of service provision by project sponsor
Project Status
RAG Status
Time
RED
Cost
RED
Scope
RED
Overall
RED
RAG Commentary
Programme Manager Comment : The project manager has not issued a report for this month or last month : project status was Red in November due to lack of sign-off from Sponsor
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Roslin Research Computing Expansion
Code
RSS002
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Kenton D'Mellow
Project Sponsor
Alan Archibald
Current Stage
Close
Status
Closed
Start Date
23-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
12-May-2017
Programme Priority
8
Overall Priority
Normal
Category
Discretionary

Documentation