Report for December 2019
- Report Date
- December 2019
Achievements
- New date for implementation into LIVE arranged with everyone
Issues
- Deployment into LIVE postponed because of staff absence
- Milestones to be replanned because of postponement
Next steps
- Revise outstanding milestones
- Carry out LIVE upgrade with business partners and vendor
- Implement SSO changes
Milestones
| Deliver | Delivery of upgrade | 05-Feb-2020 | No |
| Deliver | Delivery sign-off (Upgrade) | 11-Feb-2020 | No |
| Deliver | Delivery of SSO changes | 18-Feb-2020 | No |
| Deliver | Delivery sign-off (SSO) | 24-Feb-2020 | No |
| Close | Project closure | 28-Feb-2020 | No |
- Approved budget
- 33.0 days
- Activity this month
- 2.0 days
- Activity this year
- 19.5 days
- Activity to date
- 20.4 days
- Estimate to complete current year
- 11.3 days
- Estimate to complete future years
- 0.0 days