Report for October 2019
- Report Date
- October 2019
Achievements
- TEST environment upgraded to v3.1 (auto-patching now in place)
- Agreement on changes to Shibboleth reached
Issues
- Milestones replanned to allow greater time for UAT and SSO changes
Next steps
- Carry out UAT and sign off test upgrade
- Schedule LIVE upgrade with business partners and vendor
Milestones
| Accept | Integration & Acceptance complete | 19-Nov-2019 | No |
| Deliver | Delivery of upgrade | 26-Nov-2019 | No |
| Deliver | Delivery sign-off (Upgrade) | 03-Dec-2019 | No |
| Deliver | Delivery of SSO changes | 05-Dec-2019 | No |
| Deliver | Delivery sign-off (SSO) | 12-Dec-2019 | No |
| Close | Project closure | 19-Dec-2019 | No |
- Approved budget
- 33.0 days
- Activity this month
- 5.9 days
- Activity this year
- 13.2 days
- Activity to date
- 15.0 days
- Estimate to complete current year
- 16.9 days
- Estimate to complete future years
- 0.0 days