Report for October 2019

Report Date
October 2019

Achievements in Last Period:

  • Project initiated
  • Project Brief written and issued for review.

Issues:

  • None.

Next Steps:

  • Preparations for deployment of v5.16.1 to the development environment.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
50.0 days
Activity this month
4.5 days
Activity this year
4.5 days
Activity to date
4.5 days
Estimate to complete current year
45.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Pure Annual Upgrades v5.16 to v5.18
Code
RIS011
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Kevin Hone
Project Sponsor
Dominic Tate
Current Stage
Execute
Status
In Progress
Project Classification
Run
Start Date
14-Oct-2019
Planning Date
08-Nov-2019
Delivery Date
31-Jan-2020
Close Date
30-Sep-2020
Overall Priority
Highest
Category
Compliance

Documentation