Report for November 2019
- Report Date
- November 2019
Achievements in Last Period
- UAT Completed and signed off
- Prep for Cloud Portal - meeting with Elsevier held on 6th November
- Acceptance review and sign off approved
- Deployment to Live completed successfully on 19th November - Pure live environment upgraded to 5.15.2-1 and Java Open JDK completed
- No impact on application since deployment
- Deployment Review sign off completed and approved
Issues
- Review budget on closure and return days back to RIS Programme
- Agreement for Cloud Portal work to move to RIS011
Next Steps
- Complete Closure report and gain approval from project team
- Submit for closure to be completed
The project status is GREEN
- Approved budget
- 115.0 days
- Activity this month
- 3.3 days
- Activity this year
- 22.9 days
- Activity to date
- 72.8 days
- Estimate to complete current year
- 4.0 days
- Estimate to complete future years
- 0.0 days