Report for July 2017

Report Date
July 2017

Achievements in Last Period

  • Completed testing in DEV environment
  • Deployed v2.3 changes to TEST environment
  • Completed user acceptance testing on existing business processes which use Worktribe, and identified changes
  • Completed integration testing, incorporating the data feeds between Worktribe and UoE systems, and with the external reporting solution
  • Scheduled upgrade of LIVE to v2.3
  • Agreed implementation plan with service owner and supplier
  • Deployed upgrade to LIVE of v2.3 and sign off achieved

Issues

Open issues

  • None noted

Closed issues

  • Clarification was received about the application of the Apprenticeship Levy, its impact on data feeds and systems including Salary Forecasting

  • Agreement to place out of scope any work to link up UoE DEV interfaces with new Worktribe DEV environment - to be taken forward in a separate Finance project

  • Removed potential dependency with INF121 (Oracle upgrades to 12c) - as they are significantly behind our own timescales in terms of promoting changes through the environments

  • Release notes not in business language - they were translated and more context provided by supplier, on request

  • Mismatch in subversion number between DEV and TEST - the business lead has provided feedback this was unsatisfactory but for this project, we moved on by testing the differences and have reiterated the LIVE environment must have the same subversion number as TEST

  • Issues found by RSO in testing Apprenticeship Levy in DEV and TEST environments were raised and resolved

 

Next Steps

  • Deployment signoff and close project
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
50.0 days
Activity this month
6.4 days
Activity this year
11.6 days
Activity to date
11.6 days
Estimate to complete current year
39.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Worktribe Upgrade v2.3 & Apprenticeship Levy
Code
RES070
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Ben Armstrong
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Start Date
26-May-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
11-Aug-2017
Overall Priority
Normal
Category
Discretionary