Report for June 2017
- Report Date
- June 2017
Achievements in Last Period
- V2.2.223 deployment sign-off achieved on 6th June
- Closure report circulated and signed-off with comments from Janet Ball (RSO)
Issues
- No showstoppers
- Some issues being managed as business-as-usual issues via Unidesk and the Worktribe Tracker (ERI appearing in multi-partner projects, some output bugs, the supplement bug)
- There are workarounds in place
- These issues have been reported to supplier Worktribe Ltd via FIS users and IS L & UC , and will be managed as BAU issues until resolved by a future release
Next Steps
- Close project
Milestones
Acceptance sign-off - 2nd May (ACHIEVED)
Deployment to LIVE - Tues 16th May (ACHIEVED)
Deployment review sign-off - Tues 6th June (ACHIEVED)
Closure - Fri 30th June ( ACHIEVED)
- Approved budget
- 117.0 days
- Activity this month
- 2.0 days
- Activity this year
- 90.0 days
- Activity to date
- 90.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days