Report for June 2017
- Report Date
- June 2017
Achievements in Last Period
- Meetings with programme manager to ascertain where we are
- Potential contractor lined up to start this w/c 10/07 as they have the Oracle experience necessary for this migration.
- Dev Tech resource request submitted for this start date to secure the contractor's time.
Issues
- Delay as no Dev Tech resource is available.
- Project had an allocation of 29 days in 16/17 and 10 days in 17/18. Due to not being able to get resource to start, a re-estimation of effort has meant that we will look to do 14 days in 16/17 and 20 in 17/18.
Next Steps
- Review project activity which was completed prior to suspension
- Re-plan and re-estimate effort together with revised milestones once we know when a resource is available.
- Assign resource and commence the DEV migration
Milestones
To be re-planned once we have resource.
- Approved budget
- 45.0 days
- Activity this month
- 2.0 days
- Activity this year
- 3.0 days
- Activity to date
- 18.0 days
- Estimate to complete current year
- 13.0 days
- Estimate to complete future years
- 20.0 days