Report for Jan 2017
- Report Date
- January 2017
Achievements this period
- None - project suspended
Issues
No new issues
Dependancies
Wiki and JIRA should be migrated to 12c first
RES60 Phase 1 successfully deployed to LIVE ( DONE - 9-Nov 2016)
Implementing v5.6.4-6 (without 12c supporting patch) to fix synch issues in LIVE production
Completing RES065 first - replacing PURE App tier with VMs
Implementing v5.7 (with 12c supporting patch)
Available resource
Next Steps
Project to re-start in Mar 2017 after suspension
https://www.projects.ed.ac.uk/project/res062/issues/6
Original project suspension approved at WIS
https://www.wiki.ed.ac.uk/display/insite/Applications+WIS+Notes+-+29+July+2016
- Approved budget
- 45.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 16.0 days
- Estimate to complete current year
- 29.0 days
- Estimate to complete future years
- 0.0 days