RES062: PURE Upgrade to Oracle 12c Status Report as@ 27/07/16
- Report Date
- July 2016
Achievements this period
Background tasks undertaken:
- Update TAD/Investigate CMDB entry
- Build record 12c migration/Update migration including interface steps
- Environment - associated firewalls/Create accounts
Issues
PURE upgrade to Oracle 12c within 15/16 is no longer possible
https://www.projects.ed.ac.uk/project/res062/issues/2
Dependancies
Wiki and JIRA having been migrated to 12c first
RES60 successfully completing TEST phase
Implementing v5.6 (with/without 12c supporting patch)
Change Freeze
Available resource
Next Steps
Project suspension ( Approved for 2 months)
https://www.projects.ed.ac.uk/project/res062/issues/6
Approved at WIS
https://www.wiki.ed.ac.uk/display/insite/Applications+WIS+Notes+-+29+July+2016
Milestones - post suspension
Target date | Title | Complete |
27/05/16 | Planning | YES |
24/01/17 (14/11/16) | Delivery | NO |
27/03/17 (13/01/17) | Closure | NO |
- Approved budget
- 45.0 days
- Activity this month
- 3.0 days
- Activity this year
- 15.6 days
- Activity to date
- 15.6 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 29.0 days