June 2016 draft
- Report Date
- June 2016
Achievements this period
Business Requirements Document signed off
Background tasks established and recorded on ASTA/Plan
WIS comments addressed
Established patch required for 5.4.2 to be supported by 12c
Issues
PURE upgrade to Oracle 12c within 15/16 is no longer possible
https://www.projects.ed.ac.uk/project/res062/issues/2
Next Steps
Pending Decisions
Implement the backlog of patches prior to migrating PURE to 12c. Approx duration 8 weeks or
Holdback all patches until PURE has been migrated to 12c and then implement
Dependancies
Wiki and JIRA having been migrated to 12c first
RES60 successfully completing TEST phase
Implementing v5.6 (with/without 12c supporting patch)
Change Freeze
Available resource
Milestones
Target date | Title | Complete |
27/05/16 | Planning | YES |
14/11/16 | Delivery | NO |
13/01/17 | Closure | NO |
- Approved budget
- 45.0 days
- Activity this month
- 5.0 days
- Activity this year
- 12.2 days
- Activity to date
- 7.1 days
- Estimate to complete current year
- 5.1 days
- Estimate to complete future years
- 27.7 days