PURE Upgrade to Oracle 12c
- Report Date
- May 2016
Achievements this period
Planning complete/ Project Brief Signed Off/WIS SIgn Off
3Point Estimate completed/ Resource secured in principle
Business Requirements drafted based on SAS001
Issues
PURE upgrade to Oracle 12c within 15/16 is no longer possible
https://www.projects.ed.ac.uk/project/res062/issues/2
Next Steps
Draft Business Requirements Document
BRD Sign Off
Draft Technical and System design documents/UAT implementation/ Test scripts etc where ever possible
Address WIS comments 27/05
Pending Decisions
Implement the backlog of patches prior to migrating PURE to 12c. Approx duration 8 weeks. Based on whether the current version of PURE (5.4.2) is supported or
Implement v5.7 before migrating PURE to 12c as current version 5.4.2 is not supported but no further patches or
Holdback all patches until PURE has been migrated to 12c and then implement
Dependancies
Business desire to deliver with 15/16 Wiki and JIRA having been migrated to 12c first
RES60 successfully completing TEST phase Change Freeze
Available resource
Milestones
Target date | Title | Complete |
27/05/16 | Planning | YES |
14/11/16 | Delivery | NO |
13/01/17 | Closure | NO |
- Approved budget
- 45.0 days
- Activity this month
- 4.5 days
- Activity this year
- 7.1 days
- Activity to date
- 7.1 days
- Estimate to complete current year
- 13.6 days
- Estimate to complete future years
- 23.9 days