Report for October 2017
- Report Date
- October 2017
Achievements in Last Period
- Migrate to TEST achieved
- Integration testing passed.
- UAT passed
- Deployment to LIVE achieved
- Budget change approved
Issues
- None
Next Steps
- Deployment sign off review
- Closure report write-up and distribute for review
- Project closure
Milestones
14-Nov-2017 | Deployment sign off review |
30-Nov-2017 | CLOSURE |
- Approved budget
- 45.0 days
- Activity this month
- 17.0 days
- Activity this year
- 44.0 days
- Activity to date
- 66.0 days
- Estimate to complete current year
- 2.5 days
- Estimate to complete future years
- 0.0 days